The Albanese Government has released updated cost estimates for the Snowy 2.0 pumped hydro project showing a target cost of $22 billion and an allowance for costs to reach $25 billion, according to a ministerial statement. The 2,200 MW project was originally budgeted at $2 billion with an expected start date in 2021.
A project reset three years ago revised costs to $12 billion with first power projected for late 2027, but the reassessment now puts first power in early 2029 and full operations later that year. The government said it received the corporate plan update two days before the statement and that a new contracting model will be applied to venture partners and contractors, linking financial outcomes to delivery performance.
The head contractor Future Generation Joint Venture cited adverse geological and hydrogeological conditions encountered during tunnelling as a key cost driver outside the control of either party. Tunnel boring machines were slowed or stopped by variations in rock strength, groundwater inflows and the way rock behaves during excavation.
One machine, Florence, became stuck in February 2023 after hitting soft ground roughly 150 metres into excavating a 15-kilometre tunnel. A fourth machine, Monica, was approved in September 2024 to handle conditions through the Long Plain Fault Zone that made use of the original first machine impractical.
The project covers 37 kilometres of tunnels and underground caverns within Kosciuszko National Park, which restricted the scope of initial ground investigations. The initial ground survey used approximately 22 boreholes, averaging around 760 metres apart, with the widest gap reaching 1.75 kilometres. Former senior energy executive Ted Woodley told RenewEconomy that the scarcity of initial drilling was difficult to understand, noting that no constraints appeared to have been imposed by the national parks authority.
Dennis Barnes, Snowy Hydro's chief executive, told ABC News he was deeply disappointed by the cost outcome but said the project now requires many more workers for a longer time than anticipated in 2023, with labour accounting for 80% of costs. Machine tunnelling was 65% complete and cavern excavation 90% complete, with construction of the underground power station already under way. Barnes said he could not rule out further cost increases beyond the current targets, citing the unprecedented complexity of the work.
The government said Snowy 2.0 is a critical project for Australia's energy future despite the cost increases, and that its value to the National Electricity Market has materially grown. The government said it would continue providing full and transparent updates and is working with Snowy Hydro toward an appropriate capital structure to address the cost increase. The revised costs exclude borrowing costs, additional transmission needed to connect the project to the grid, and environmental impacts from construction within the national park.
AEMO has confirmed the project is crucial for maintaining reliability in the National Electricity Market, meaning its completion has direct implications for electricity supply security. GHD scenario modelling found Snowy 2.0 could hold peak wholesale prices to nearly 70% below what an equivalent battery solution would produce during a winter week of low wind and solar output after NSW coal exits the market.
Official statements: Ministerial statement
Reporting: ABC News, RenewEconomy
Written by Pick & Scroll News from the reporting and documents linked above.